NEW CONSTRUCTION OF A SHEET PILE WALL FOR SLOPE STABILIZATION
The gravity wall in Gennerstraße in Hürth was to be replaced by a sheet pile wall clad with L-stones in spring 2018. For the executing construction company, we took over the entire technical planning of the sheet pile wall and supplied the necessary material. A total of 54 tons of L604 steel sheet pile sections in lengths of six to 9.5 meters were used.
The construction work was carried out in sections, i.e. part of the existing concrete wall was demolished and the sheet pile wall was installed in its place. Due to the existing historical buildings, we used pre-drilling and vibration for the installation. We produced the required radius at a road intersection with seven construction piles from our own production.
The project was calculated to take four weeks to complete. Thanks to our customized logistics concept and high-performance machine technology, it was completed in only 18 days.


you might also be interested in
-
Saxony-Anhalt is also battening down its hatches
Since the “flood of the century” in 2002, Saxony-Anhalt has completed a whole range of flood defence measures, especially for upgrading dykes. One weak spot was the Elbtor alongside the River Elbe in Schönebeck.
To the post -
Trenchless Crossing
New laying of an underground power line from the central substation to the north substation closes the inner-city power line network and increases the security of supply in the urban area.
To the post -
Floor Renovation in a New Dimension in Ingolstadt
When carrying out the honeycomb process, the experts resorted to the idea of attaching a free-riding MÜLLER MS-40 HFV vibratory machine from terra infrastructure to a Liebherr carrier machine.
To the post