terra infrastructure provided installation equipment and sheet pile to Teras Australia for the upgrade of their Marine barge terminal located at East Arm Darwin NT.
The project included 387 x sheets of Larssen L720 sheetpile at a length of 10m, for the construction of the 232Lm wall.
Installation was carried out by Advance civil utilising terra infrastructure’s ABI 14/18 Piling Rig to set and drive the piles, then using a BSP CX110 impact hammer to back drive to the required depth.

you might also be interested in
-
Saxony-Anhalt is also battening down its hatches
Since the “flood of the century” in 2002, Saxony-Anhalt has completed a whole range of flood defence measures, especially for upgrading dykes. One weak spot was the Elbtor alongside the River Elbe in Schönebeck.
To the post -
Foundation for first nuclear power plant in Bangladesh
In Ruppur, about 180 kilometres west of the capital Dhaka, the first national nuclear power plant is to secure Bangladesh's energy supply from the end of 2023.
To the post -
Rehabilitation of a Landfill
For groundwater capture, the landfill was provided with sheet pile walls, which were coated on both sides and provided with a permanent interlock seal.
To the post